To a prepared base, sweep off excess debris, lightly water with a water tanker or
watering-
Bags to be placed on the prepared base at 1m intervals.
Depending on the required thickness, measured square bars are placed on either side of the lanes to ensure the thickness and width of each lane of the road.
The bags are then opened and the product spread using rakes and spades.
Once material is spread a T -
Directly after completing the laying process, water is again applied until the product achieves its optimal tackyness in order to achieve the required finish.
Compact according to the particular road specification. Pneumatic or steel rollers
are highly recommended for an excellent finish. Using labour, hand-
The wheels of the rollers should be kept wet as this aids in bringing the fines in the product to the surface, which ultimately seals and waterproofs the road surface.
For best results, allow 4 -